First Light...

Our first electrical light in the house :-) Yes - we turned it off again before leaving ;-)

Tim, surveying this week's progress, and admiring the view from the back entrance stairway :-)

And then we discovered that not only do we have a working interior light but we also have RUNNING WATER!
At this point, the cabinets are all installed in the kitchen, master bathroom, and guest bathroom. Doors and handles still need to be applied to the cabinets but the basics are in and our fridge has been set in its place as well.
Slate tile is all done and grouted, as is the dog wash tile.
Doorways have been trimmed, and lots of progress made on the crown molding throughout the house.
The dehumidifiers and heaters are still running. Not sure what the moisture level is at or when they anticipate being able to start the hardwood floors. We should learn more next week at our next site meeting.
More photos here, of this week's progress!